Evaluation of the Incidences of Risk Occurrence and Severity in PPP-Procured Mass Housing Projects (PPP-MHPs) in Abuja, Nigeria

World Journal of Civil Engineering and Architecture | Vol 2, Issue 1

Table 6. Level of Severity of Risk Factors in PPPprocured Mass Housing Projects- Cont’d

Risk FactorsRisk SeverityStd. DeviationRankAsymp.Sig
Land Grabbing/Encroachment5.520.77180.388
Inadequate distribution of Authority between Partners5.510.76519.000*
Construction cost overrun5.500.56720.000*
Prolonged negotiation period prior to initiation5.480.58621.000*
Interest rate volatility5.470.7622.000*
Poor Financial Market5.460.96323.000*
Poor decision-making process5.450.604240.931
Influential Economic Events (Boom/Recession)5.410.78525.000*
High Bidding cost5.380.848260.029
Financial attraction to project investors5.361.047270.064
Delay in Project approvals and permits5.340.641280.540
Change in Government5.301.073290.031
Public opposition to the mass housing projects5.151.286300.001*
Weather5.081.09231.000*
Inflation rate volatility5.060.99232.000*
Operation cost overrun5.040.71633.000*
Insolvency/default of Subcontractors and Suppliers5.020.87334.000*
Inability to service debt4.990.895350.010
Excessive contract variation4.930.83236.000*
Organization and Coordination risk4.920.80537.000*
Bankruptcy of the investors (OPS)4.871.028380.011
Operational revenue below the projection4.800.71939.000*
Geotechnical conditions4.790.94640.000*
Different working methods/know-how between partners4.750.78141.000*
Lack of tradition of private provision of public services4.700.999420.052
Lack of Government guarantee4.701.091430.140
Legislation change/Inconsistencies4.680.861440.322
Environment4.670.639450.062
Inconsistencies in Government Policies4.661.10546.000*
Availability of appropriate labour/material4.640.912470.014
Third party tort liability4.610.692480.001*
Possible expropriation/nationalization of assets4.600.91249.000*
Rate of Return restrictions4.601.17750.000*
Low operating productivity 4.590.61951.000*
Competition risk4.550.83752.000*
Import and Export restriction4.490.62553.000*
Poor Quality of Workmanship4.480.814540.041
Unproven Engineering techniques4.450.69455.000*
Design deficiencies4.401.15560.007*
Residual value (After concession period)4.380.77157.000*
Staff crises4.360.589580.043
Industrial regulation change4.300.75559.004*
Late design changes4.301.041600.620
Change in tax regulation4.291.01661.000*
Cultural differences between the main Stakeholders4.231.18962.000*
Strong Political opposition4.140.91363.000*