Evaluation of the Critical risk factors in PPP - procured Mass Housing Projects in Abuja Nigeria - A fuzzy synthetic evaluation (FSE) approach
World Journal of Civil Engineering and Architecture
| Vol 2, Issue 1
Table 6. Membership Function (MF) for CRFs and CRFG in PPP-procured Mass HousingProjects (Risk Severity)
| CRFs and PRFs | Weighting (wn) for CRFs | Membership function for level 3 CRFs | Membership function for level 2 CRFG |
| Financial and Macroeconomic risk (CRFG 1): u1 | (0.00,0.00,0.02,0.08,0.21,0.56,0.12) | ||
| Availability of Finance, u11 | 0.116 | (0.00,0.00,0.00,0.00,0.02,0.41,0.57) | |
| High Finance cost, u12 | 0.111 | (0.00,0.00,0.00,0.00,0.06,0.66,0.28) | |
| Unstable Value of Local Currency, u13 | 0.101 | (0.00,0.00,0.00,0.05,0.22,0.73,0.00) | |
| Lack of credit worthiness, u14 | 0.101 | (0.00,0.00,0.03,0.01,0.21,0.74,0.01) | |
| Influential Economic Events (Boom/Recession), u15 | 0.096 | (0.00,0.00,0.00,0.16,0.29,0.53,0.02) | |
| High Bidding cost, u16 | 0.096 | (0.00,0.00,0.02,0.14,0.31,0.50,0.03) | |
| Poor Financial Market, u17 | 0.097 | (0.00,0.00,0.07,0.08,0.19,0.62,0.04) | |
| Financial attraction to project investors, u18 | 0.095 | (0.00,0.00,0.12,0.00,0.32,0.50,0.06) | |
| Interest rate volatility, u19 | 0.097 | (0.00,0.00,0.01,0.13,0.24,0.62,0.00) | |
| Inflation rate volatility, u110 | 0.090 | (0.00,0.02,0.00,0.27,0.36,0.30,0.05) | |
| Legal and Socio-political risk (CRFG 2): u2 | (0.00,0.01,0.01,0.06,0.18,0.70,0.04) | ||
| Corruption and lack of respect for Law, u21 | 0.118 | (0.00,0.00,0.00,0.02,0.00,0.90,0.08) | |
| Non-involvement of the host community, u22 | 0.116 | (0.00,0.00,0.02,0.00,0.07,0.86,0.05) | |
| Poor execution of Housing Policies, u23 | 0.115 | (0.00,0.00,0.00,0.05,0.06,0.86,0.03) | |
| Wrong perception of housing need by low-income earners, u24 | 0.117 | (0.00,0.00,0.00,0.00,0.06,0.91,0.03) | |
| Illegal Title to Land, u25 | 0.116 | (0.00,0.00,0.00,0.01,0.10,0.87,0.02) | |
| Poor decision making process, u26 | 0.107 | (0.00,0.00,0.00,0.05,0.47,0.47,0.01) | |
| Change in Government, u27 | 0.188 | (0.00,0.01,0.10,0.05,0.31,0.48,0.05) | |
| Land Grabbing/Encroachment, u28 | 0.108 | (0.00,0.00,0.00,0.15,0.21,0.62,0.02) | |
| Public opposition to the mass housing projects, u29 | 0.101 | (0.00,0.04,0.09,0.20,0.11,0.49,0.07) | |
| Operation and Organization risk (CRFG 3): u3 | (0.00,0.00,0.01,0.06,0.21,0.71,0.01) | ||
| Inadequate experience in PPP, u31 | 0.205 | (0.00,0.00,0.00,0.05,0.12,0.83,0.00) | |
| Inadequate distribution of responsibility and risks, u32 | 0.204 | (0.00,0.00,0.01,0.06,0.11,0.80,0.02) | |
| Risk regarding Pricing of Product/service, u33 | 0.197 | (0.00,0.00,0.01,0.08,0.25,0.66,0.00) | |
| Lack of Commitment from Public/Private Partners, u34 | 0.199 | (0.00,0.00,0.00,0.06,0.28,0.64,0.02) | |
| Inadequate distribution of Authority between Partners, u35 | 0.195 | (0.00,0.01,0.01,0.06,0.29,0.63,0.00) | |
| Design and Project Selection risk (CRFG 4): u4 | (0.00,0.00,0.01,0.03,0.27,0.68,0.01) | ||
| Land acquisition and Site availability, u41 | 0.262 | (0.00,0.00,0.02,0.00,0.03,0.94,0.01) | |
| Level of Demand for the mass housing projects, u42 | 0.258 | (0.00,0.00,0.00,0.01,0.17,0.80,0.02) | |
| Prolonged negotiation period prior to initiation, u43 | 0.243 | (0.00,0.00,0.00,0.05,0.42,0.53,0.00) | |
| Delay in Project approvals and permits, u44 | 0.236 | (0.00,0.00,0.01,0.06,0.51,0.42,0.00) | |
| Construction risk (CRFG 5): u5 | (0.01,0.00,0.00,0.06,0.31,0.61,0.02) | ||
| Construction time delay, u51 | 0.337 | (0.00,0.00,0.00,0.01,0.36,0.63,0.00) | |
| Construction cost overrun, u52 | 0.330 | (0.00,0.00,0.00,0.04,0.43,0.53,0.00) | |
| Force majeure, u53 | 0.333 | (0.02,0.00,0.00,0.13,0.13,0.67,0.05) | |