Evaluation of the Critical risk factors in PPP - procured Mass Housing Projects in Abuja Nigeria - A fuzzy synthetic evaluation (FSE) approach
World Journal of Civil Engineering and Architecture
| Vol 2, Issue 1
Table 7. Membership Function (MF) for Overall Risk Level in PPP-procured Mass HousingProjects
| Critical Risk Group (CRFG) | Weighting (wi) for CRFG | Membership function level 2 (CRFG) | Membership function of level 1 (ORL) |
| Risk probability (from level 2 to 1) | 0.00,0.01,0.01,0.08,0.23,0.59,0.08 | ||
| Financial and Macroeconomic risk (CRFG 1): u1 | 0.327 | 0.00,0.00,0.02,0.09,0.21,0.54,0.15 | |
| Legal and Socio-political risk (CRFG 2): u2 | 0.293 | 0.00,0.00,0.01,0.10,0.17,0.68,0.04 | |
| Operation and Organization risk (CRFG 3): u3 | 0.159 | 0.00,0.01,0.01,0.06,0.25,0.67,0.00 | |
| Design and Project Selection risk (CRFG 4): u4 | 0.130 | 0.00,0.01,0.02,0.05,0.22,0.59,0.11 | |
| Construction risk (CRF 5): u5 | 0.091 | 0.01,0.00,0.00,0.09,0.51,0.38,0.01 | |
| Risk severity (from level 2 to 1) | 0.00,0.00,0.01,0.06,0.22,0.64,0.07 | ||
| Financial and Macroeconomic risk (CRFG 1): u1 | 0.322 | 0.00,0.00,0.02,0.08,0.21,0.56,0.12 | |
| Legal and Socio-political risk (CRFG 2): u2 | 0.292 | 0.00,0.01,0.01,0.06,0.18,0.70,0.04 | |
| Operation and Organization risk (CRFG 3): u3 | 0.161 | 0.00,0.00,0.01,0.06,0.21,0.71,0.01 | |
| Design and Project Selection risk (CRFG 4): u4 | 0.129 | 0.00,0.00,0.01,0.03,0.27,0.68,0.01 | |
| Construction risk (CRFG 5): u5 | 0.095 | 0.01,0.00,0.00,0.06,0.31,0.61,0.02 | |