Evaluation of the Incidences of Risk Occurrence and Severity in PPP-Procured Mass Housing Projects (PPP-MHPs) in Abuja, Nigeria

World Journal of Civil Engineering and Architecture | Vol 2, Issue 1

Table 4. Level of Risk Occurrence/Probability in PPPProcured Mass Housing Projects Cont.

Risk FactorsRisk ProbabilityStd. DeviationRankAsymp. Sig
Operational revenue below the projection4.690.62239.000*
Inconsistencies in Government Policies4.680.711400.143
Environment4.640.68141.000*
Third-party tort liability4.570.65742.000*
Different working methods/know-how between partners4.540.789430.080
Change in tax regulation4.500.795440.852
Residual value (After the concession period)4.470.76445.000*
Design deficiencies4.470.943460.548
Availability of appropriate labor/material4.450.763470.019
Excessive contract variation4.430.71548.000*
Low operating productivity 4.410.823490.025
Rate of Return restrictions4.390.94050.000*
Lack of Government guarantee4.391.001510.009
Industrial regulation change4.330.72652.005*
Legislation change/Inconsistencies4.280.715530.092
Cultural differences between the main Stakeholders4.271.159540.672
Insolvency/default of Subcontractors and Suppliers4.250.65555.000*
Strong Political opposition4.210.68556.000*
Unproven Engineering techniques4.200.71957.000*
Import and Export restriction4.190.64558.001*
Poor Quality of Workmanship4.120.75459.000*
Possible expropriation/nationalization of assets4.120.75560.000*
Geotechnical conditions4.120.895610.289
Staff crises4.110.68662.000*
Late design changes4.000.851630.016